2022 Street Improvement Projects
This Project Includes
Contract 22-101
- Portland Area (rehabilitation)
- Ridges Area (rehabilitation)
- Buck Hill Road (rehabilitation)
Contacts:
- Project Inspector: Cody Pietz, Phone: 952-356-6839
- Project Manager: Logan Vlasaty Phone: 952-895-4457
Contract 22-102
- Heart of the City (rehabilitation)
- Colonial Park Area (reclamation)
- Southcross Heights (reclamation)
- West Park (reclamation)
- Burnell Park (reclamation)
Contacts:
- Project Inspector: Tim Zahratka, Phone: 612-619-5892
- Project Manager: Logan Vlasaty Phone: 952-895-4457
Reclamation work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.
Rehabilitation work consists of replacing the top 2" of pavement and minor utility work.
10/19 Updates:
Look here for weekly updates to each project area during construction
22-101
- Both areas are substantially complete
- Buck Hill Road
- Ridges Area: pending installation of the flashing light system for the two pedestrian crossings on Nicollet Blvd. The system will be installed as soon as it is delivered - there has been supply chain issues contributing to the delayed delivery.
22-102
- All areas are now substantially complete:
- Colonial Park
- Southcross Heights
- West Park
- Burnell Park
If you would like to receive update notifications via email and/or text, please click on the 'Subscribe' button near the top of this page and fill out the required information.
Special Assessment Payments
The interest free pre-payment period for special assessments is available through 11/15/2022. There are three payment options:
- In person at City Hall (open M-F; 8:00am - 4:30pm)
- Via mail - must be received in our office by 11/15/2022
- Online until 7:00pm on 11/14/2022
Assessments not paid by 11/15/2022 will be sent to Dakota County Taxation for certification to your 2023 property taxes.
Please call Molly at 952-895-4495 with any questions.
Interactive Web Map
When looking at the map legend, 'Substantially Complete' means that the roadwork is mostly done and only minor work remains such as clean-up or turf establishment, etc. Once a project is 100% completed, it will be removed from this map.
Timeline
- Feb. 16, 2021: Council ordered preliminary report for the 2022 Street Improvement Projects
- April-October 2021: Staff studied project areas and drafted a preliminary report
- Sept. 22, 2021: Open house at James Avenue cul-de-sac
- Sept. 23, 2021: Open house at Hollows Park
- Sept. 29, 2021: Open house at City Hall
- Sept. 30, 2021: Open house at Nicollet Commons Park
- Dec. 7, 2021: Council received preliminary report and call for public improvement hearing
- Jan. 5, 2022: Ridges Area virtual Open House via Zoom
- Feb. 15, 2022: Council held public improvement meeting
- February 2022: Received bids
- April 19, 2022: Council to hold assessment hearing and award contracts
- April - October 2022: Construction occurs
- Nov. 15, 2022: Assessment pre-payment deadline
- Spring 2023: Final completion
Dates are tentative and subject to change.