2021 City Street Improvements

Preliminary Report Available for Viewing

The City has prepared a preliminary report summarizing the existing conditions and proposed improvements for the projects.  A copy of the preliminary report is available for viewing here.

The Strategies

Street Improvement Strategies

Learn More About Reclamation and Rehabilitation

Click here to learn more about the street reclamation process Opens in new window

Click here to learn more about the street rehabilitation process Opens in new window

Timeline

  • October 30, 2020: Mail informational letter and brochure to affected property owners
  • Early November 2020: Online information and video presentation available
  • November 18, 2020 from 4 pm to 6 pm:  Drive-up open house at Coventry Court Park
  • November 19, 2020 from 4 pm to 6 pm: Drive-up open house at Burnahaven Park
  • December 8, 2020: Council to accept preliminary report on proposed 2021 street improvements and call for public hearing
  • January 19, 2021: Council to hold public hearing on 2021 Street Improvement Projects and authorize bidding
  • February/March 2021: Receive bids
  • March/April 2021: Council to hold assessment hearing and award improvement contract(s) for 2021 street improvements
  • April 2021 to October 2021: Construction season for 2021 street improvements
  • October 2021: Post-construction customer satisfaction survey
  • November 15, 2021: Special assessment pre-payment deadline
  • Spring 2022: Final completion
  • *Dates are tentative and subject to change

Proposed 2021 City Street Improvements

The map below show the proposed 2021 City street improvements. Please note that the strategies shown are subject to change based on information gathered during the planning process.  More information is available via the video presentation above or the informational slides.

Interactive Web Map

To find out more information about any projects on the map below click on the map item for more information.  Click >> for to see the map legend.  Click "View larger map" to access a full size interactive map.

  1. John Schmeling

    Assistant City Engineer
    Phone: 952-895-4457