Overview

Reclamation work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.  These areas include:

  • River Hills Drive
  • Happe Area
  • North Highway 13 Frontage Road

Rehabilitation work consists of replacing the top 2" of pavement and spot replacement of curbs.  These areas include:

  • Parkwood Drive
  • Travelers Trail

Contacts

Links

Updates:

See phasing map below for reference

Updates for the week of July 6-11, 2020

See updates below by phase.  Click the Weekly Construction Update (PDF) for a printable pdf version with additional information.

Phase 1

  • Finish mulching and seeding disturbed boulevard areas
  • Repair damaged landscape items

Phase 2 

  • Milling pavement
  • Grading and paving full depth pavement replacement area on southbound lanes of 12th Avenue

Phase 3

  • Milling pavement
  • Paving final layer of asphalt

Phase 4

  • Paving base layer of asphalt (Delayed from previous schedule due to rain)

Phase 5

  • Grading road base (Delayed from previous schedule due to rain)
  • May pave base layer of asphalt mid to late week