130th Street
Subscribe to email updates
New Update
September 22, 2017
The Contractor is scheduled to place the first layer of asphalt on or around Tuesday, September 26, 2017.
Older Updates
September 13, 2017
The Contractor will be milling off the asphalt on Friday and Saturday 9/15-9/16.
September 8, 2017
The Contractor is tentatively scheduled to
start in this project area on or around
September 13, 2017.
July 11, 2017
The Contractor has delayed the start of this project area. A new start date will be posted when it becomes available.
June 19, 2017
The Contractor has delayed the
start of this project area to
July 10, 2017.
June 8, 2017
The project on
130th Street is scheduled to start Monday 6/19/17. Construction will follow the general sequence described in the May 31, 2017 update below.
May 31, 2017
The City has awarded a contract to Park Construction Inc. to perform a maintenance overlay on 130th Street from Parkwood Drive to County Road 11 as part of the 2017 Maintenance Overlay Project.
The project on 130th Street is expected to start around mid June. This project area is expected to take about three (3) weeks to complete and will generally constructed in the following sequence:
-Remove and replace damaged curb.
-Remove the blacktop via milling.
-Mix and finish the aggregate base.
-Adjust miscellaneous utilities.
-Restore disturbed areas.
-Pave the streets.
There will be no assessments for this work.
A
project start notification letter was sent to the affected residents. Regular updates will be posted to this page as construction occurs.