New Updates

April 19, 2017

The City has awarded a contract to McNamara Contracting, Inc. for the street improvements in the North Crystal Lake neighborhood as a part of the City’s 2017 Street Reclamation Project.

A neighborhood meeting is being held on Thursday, April 27, 2017 from 3:30 to 6:00 PM in the City Council Chambers at Burnsville City Hall for property owners interested in learning more about this project. A formal letter explaining the project and providing notification of the neighborhood meeting was recently mailed to property owners.

City staff completed a preconstruction meeting with representatives from McNamara Contracting, Inc. and private utility companies. At this meeting, the project schedule was discussed. McNamara Contracting plans to start work in the North Crystal Lake area on Monday, May 15th. Work within the North Crystal Lake neighborhood is expected to be complete by the end of August. Construction activities are very weather dependent so the Contractor’s schedule may change due to weather.  

Work within the North Crystal Lake Neighborhood will be broken into 5 phases and it is anticipated that construction in each phase will last about 6-weeks. The streets within the various phases are as follows:

  • Phase 1 – Interlachen Road, Butternut Lane, Chestnut Drive, and Chestnut Circle (anticipated start date: May 15th)
  • Phase 2 – Tyacke Drive, 152nd Street East, and Swanson Circle (anticipated start date: May 29th)
  • Phase 3 – Crystal Lake Road (from Tyacke Dr. to Chicago Ave.), Crystal Drive West, Crystal Drive East, Crystal Lake Terrace, 153rd Street East (anticipated start date: June 8th)
  • Phase 4 – Oakland Avenue, Park Avenue, and 151st Street East (anticipated start date: June 19th)
  • Phase 5 – Rushmore Drive, Lead Street, 152nd Street East, and Crystal Lake Road East (from Chicago Avenue to Lac Lavon Dr.) (anticipated start date: July 10th)


Older Updates

Jan. 3, 2017


A neighborhood meeting is being held on Wednesday, January 18, 2017 from 3:30 to 6:00 PM in the City Council Chambers at Burnsville City Hall for property owners interested in learning more about this project. 

A formal letter explaining the project and providing notification of the neighborhood meeting was recently mailed to property owners, and a copy of the letter with the project area map and contacts for City staff can be viewed by clicking the link below:
 
Crystal Lake North Neighborhood Meeting Notice
Crystal Lake North Neighborhood Street Reconstruction Map