September 6, 2017
Special assessments for the project were approved by the City Council at their meeting on September 5, 2017.  Assessment costs and payment information is available in the letters sent on August 18, 2017.  Property owners wishing to pay their special assessments in-full for the street work are reminded that payment is due no later than Tuesday, October 31, 2017.  Credit card payments are not accepted for special assessments.  Questions regarding assessment payoff amounts or deferrals may be directed to Molly Stone at 952-895-4495, or .  

Older Updates

June 26, 2017

Due to a delay in materials delivery, the Contractor delayed the installation of sidewalk till this week.  Early in the week of 6/26/17 sidewalks will be poured and mid to late week the streets will be milled.  Paving is tentatively scheduled from 7/5/17 to 7/7/17.  

June 19, 2017
The Contractor will be installing pedestrian ramps in areas where sidewalk was removed later in the week of 6/19/17.  Milling of the streets may start this week.  Paving of the streets is tentatively scheduled for the week of 6/26/17.

May 23, 2017

The Contractor is planning to start work on Tuesday (5/30/17).

May 19, 2017

Due to weather the Contractor is delaying the start of this project.  The new start date will be posted on this web page when it becomes available.

May 16, 2017

The City has awarded a contract to Valley Paving, Inc. to perform the street rehabilitation project in the Greenhaven Drive area as part of the City's 2017 Street Rehabilitation Project.  The project is tentatively scheduled to start on Monday May 22, 2017.  The project is expected to take approximately six (6) weeks to complete and will generally be constructed in the following sequence: 

-Remove and replace damaged curb and driveways.
-Adjust miscellaneous utilities. 
-Restore disturbed areas.
-Mill and pave the streets.

The assessment hearing for this work is tentatively scheduled for September 5, 2017.  Properties proposed to be assessed will receive further notice of this meeting prior to that date.

A project start notification letter was sent to the affected residents.  Regular updates will be posted to this page as construction occurs.

Jan. 3, 2017

A neighborhood meeting is being held on Wednesday, January 18, 2017 from 3:30 to 6:00 PM in the City Council Chambers at Burnsville City Hall for property owners interested in learning more about this project.

A formal letter explaining the project and providing notification of the neighborhood meeting was recently mailed to property owners.  Property owners with questions are encouraged to contact the City’s Engineering Department at 952-895-4534.  A copy of the project area map can be viewed by clicking the link below:
 
Greenhaven Neighborhood Street Reconstruction Map