April 12, 2017

Ryan Contracting started construction on Lady Bird Lane on April 10th. It is anticipated that construction will take 4-6 weeks to complete. The Contractor completed the sanitary sewer replacement on April 11th. A new valve will be installed on the watermain on Thursday, April 13th requiring a temporary water shutdown to a few properties in the area. Over the next week, crews will rehabilitate existing utility structures. 

For questions about the project please contact Sarah Lloyd:  or at 952-895-4457 or call Bob Flaws at 612-328-0742. 