Project Area Map and Construction Contacts

Assessment Approval Update

Special assessments for the project were approved by the City Council at their meeting on September 6, 2016.  Assessment costs and payment information is available in the letters sent on August 18, 2016.  Property owners wishing to pay their special assessments in-full for the street work are reminded that payment is due no later than Monday, October 31, 2016.  Credit card payments are not accepted for special assessments. Questions regarding assessment payoff amounts may be directed to Molly Stone at 952-895-4495, or
.   

New Updates

August 19, 2016

Following final pavement striping and new roadway sign installation, the work on Maple Island Road is substantially complete.  Over the next few weeks, crews will be cleaning up any remaining construction debris, and will be monitoring restoration areas for weeds and re-seeding as necessary.

The City of Burnsville and McNamara Contracting thank you for your patience and cooperation as we have worked to bring you improved streets and utility infrastructure.  Property owners who have any residual concerns or questions regarding the work on the project are encouraged to contact the project inspector, Brad Mikiska, at 952-356-4506.  

Older Updates

July 21, 2016

Crews have completed grading, curb, and the first layer of pavement on Maple Island Road.  Over the next week, crews will be adjusting utility structures, backfilling curb, grading boulevard/ditch areas, performing topsoil placement and seeding, and preparing for the second layer of pavement, which is anticipated to be placed during the week of July 25th.  

July 12, 2016


Crews began reclaiming the pavement today, and anticipate this work to be completed later this week.  Crews will be grading and excavating the top 4” of reclaimed material and re-shaping the roadway surface for paving.  Reclaimed pavement will be compacted in-place so vehicles can still drive on it, although local residents are encouraged to utilize alternative access routes where possible.  

Crews will complete utility installation work at the south junction of Maple Island Road on Friday (weather permitting), and curb is anticipated to be installed late in the week of July 18th. 

July 7, 2016

Crews anticipate beginning pavement reclamation activities along Maple Island Road the week of July 11.  Traffic control signs, including “Road Closed to Through Traffic” signs will be placed at either end of the project.  Local traffic will still be able to access properties along Maple Island Road, although residential traffic is encouraged to utilize alternative access points to County Road 46 south of Crystal Lake, including Jamaica Ave. and Bluebill Bay Road.  

Work on the project is anticipated to last up to four weeks, with the roadway in an “unpaved” condition for up to three weeks. 

April 27, 02016

The Contractor has provided the City their proposed work schedule, and work on Maple Island Road will not commence until after July 4th of this year.  We will provide more detailed schedule updates on this site closer to the start of construction.

Residents are reminded of the Neighborhood Meeting being held on Monday, May 2, 2016 from 3:30 to 6:30 PM in the Large Community Room at Burnsville City Hall.  Information can be found under the April 20th update below. 

April 20, 2016

 
The City has awarded a contract to McNamara Contracting, Inc. to reclaim and re-surface Maple Island Road as part of the City’s 2016 Street Reclamation Project.  

A neighborhood meeting is being held on Monday, May 2, 2016 from 3:30 to 6:30 PM in the Large Community Room at Burnsville City Hall for property owners interested in learning more about this project and the upcoming construction schedule.

A formal letter explaining the project and providing notification of the neighborhood meeting was recently mailed to property owners, and a copy of the letter with the project area map and contacts for City staff can be viewed by clicking the link below:
 
Maple Island Road Meeting Notice


Prior to the neighborhood meeting, City staff will be meeting with the Contractor to identify the general project schedule and phasing plans.  That information will be available at the neighborhood meeting, and provided as an update on this project web page. 

Older Updates

December 28, 2015


A neighborhood meeting is being held on Thursday, January 14, 2016 from 3:30 to 6:30 PM in the City Council Chambers at Burnsville City Hall for property owners interested in learning more about this project.

A formal letter explaining the project and providing notification of the neighborhood meeting was recently mailed to property owners, and a copy of the letter with the project area map and contacts for City staff can be viewed by clicking the links below:
 
Maple Island Road Meeting Notice
Maple Island Road Street Reconstruction Map