150th Street
Email alert logoSubscribe to email updates


Project Area Map & Construction Contacts

Assessment Approval Update

Special assessments for the project were approved by the City Council at their meeting on September 6, 2016.  Assessment costs and payment information is available in the letters sent on August 18, 2016.  Property owners wishing to pay their special assessments in-full for the street work are reminded that payment is due no later than Monday, October 31, 2016.  Credit card payments are not accepted for special assessments. Questions regarding assessment payoff amounts may be directed to Molly Stone at 952-895-4495, or
.   

New Updates


August 2, 2016

With the completion of the seeding, paving, and pavement striping work, the work on 150th St. is substantially complete.  Crews will continue with cleanup work, including sewer cleaning and sign replacements, as well as punchlist items over the coming weeks. 

The City of Burnsville and McNamara Contracting thank you for your patience and cooperation as we have worked to bring you improved streets and utility infrastructure.  Property owners who have any residual concerns or questions regarding the work on the project are encouraged to contact the project manager, Brian Connolly, at 952-895-4457.  

July 26, 2016


Crews are milling the pavement on 150th St. today in preparation for paving activities, which will occur on July 27th, starting at 6:30 AM.  Crews anticipate completing paving work in one day.  Starting July 28th, 150th St. will be re-opened to traffic at CSAH 5.

Pavement striping will occur the week of August 1st, followed by final boulevard hydroseeding of all disturbed areas. 

Older Updates

July 19, 2016


This week, crews will be paving the roadway section removed as part of the PRV installation at 150th St. and CSAH 5.  Restoration crews will also be onsite to patch any remaining driveway aprons, as well as complete topsoil placement and seeding restoration along curbs and sidewalks.

Milling and paving on 150th St. is anticipated to occur July 26-27, weather dependent. 

July 12, 2016

Crews will be completing concrete work at 150th St. and CSAH 5 this week, and backfilling curb and sidewalk throughout the remainder of the project area.  Additional utility structures will also be adjusted/repaired.  

Final topsoil and seeding is anticipated to occur the week of July 18th.  

July 7, 2016


Crews have completed sidewalk and curb removals, and should be wrapping up the bulk of the concrete replacement work today.  Crews have also excavated for the placement of the pressure reducing valve station at CSAH 5, and will be setting the vault structure later today.  Interior valve connection work will occur over the next week.  Also in the coming week, crews will also begin patching around new curb and performing utility structure adjustments throughout the project area. 

June 28, 2016

Crews will begin work this week by sawcutting sidewalk and spot curb repair items.  Starting the week of July 5, 150th St. will be closed between CSAH 5 and Cherry Lane.  Crews will be excavating for a pressure reducing valve station, as well as removing and replacing the majority of concrete items throughout the project area.  Crews will also be working to adjust utility structures within the roadway.  


May 10, 2016


A construction kickoff letter was mailed to property owners on May 2 regarding the upcoming work on 150th St.  Due to both weather and material procurement delays, work is scheduled to be begin after Memorial Day (May 30).  The letter also includes a list of City inspectors who property owners and residents may contact if they have questions during the construction project.  

The first phase of work on 150th St. will include the installation of a watermain pressure reducing valve (PRV) station at CSAH 5.  This work will result in 150th St. being CLOSED at CSAH 5 for approximately two weeks while work occurs.  After the PRV is installed, 150th St. will be opened for two-way traffic while crews complete the milling and overlay work on the remainder of the roadway.  Signs will be posted of the closure date once it is determined by the Contractor. 

December 28, 2015

A neighborhood meeting is being held on Thursday, January 14, 2016 from 3:30 to 6:30 PM in the City Council Chambers at Burnsville City Hall for property owners interested in learning more about this project.

A formal letter explaining the project and providing notification of the neighborhood meeting was recently mailed to property owners, and a copy of the letter with the project area map and contacts for City staff can be viewed by clicking the link below:


150th Street - Neighborhood Meeting Notice 
150th Street - Street Rehabilitation Map