121st and Pleasant Street and Trail Improvements

Overview

  • Reclamation of 121st Street.  This work consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.
  • Reconstruction of Pleasant Avenue.  This work consists of replacing all pavement and curbs, repairing and/or upgrading storm sewers, sanitary sewers, and water mains.
  • Trail replacement on the north side of 121st and east side of Pleasant Avenue.
  • Storm sewers will be cleaned and lined, and well closures will be monitored

Project funding

  • DEED grant
  • Special assessments
  • Infrastructure Trust Fund
  • Storm Utility Fund
  • Water Utility Fund

Contacts

  • Construction Inquiries                                             Sarah Lloyd: 952-890-0509 ext. 2417
  • Assessment Inquiries                                               Molly Stone: 952-895-4495

Project Schedule

  • Construction start: Tuesday, September 3, 2019
  • First lift of pavement completed: Week of September 23, 2019
  • Final Project completion: Spring 2020
  • Assessment hearing: Spring 2020

Access During Construction

  • No on-street parking during construction beginning Tuesday, September 3, 2019
  • Access will be provided to properties along 121st Street throughout construction - there may be some short delays depending on construction activity.  Pleasant Avenue will be closed during the street reconstruction
  • City Compost site will remain open on weekends with access available