The Maple Island/Bluebill Bay Area is planned for 2019 street rehabilitation and reclamation. The street rehabilitation portion consists of spot curb repair, milling the top two inches of pavement, and placing a two-inch asphalt overlay. The street reclamation portion consists of grinding up of the existing asphalt while mixing it with the gravel base, grading, paving, storm sewer repairs and upgrades, and sanitary sewer repairs. Curbs will be spot replaced where severely cracked or broken.  This project is being managed by the City of Lakeville.  Additional information is available on their project website.

Contacts

Links

Updates

Click on your street segment on the map below or see below for updates.

July 11, 2019

Phase 8 is tentatively scheduled to begin early in the week of July 22, 2019 with curb removals.

May 22, 2019

Interactive applications with information on street rehabilitation and reclamation have been posted in the "Links" section of this page.  Please see the Street Rehabilitation Informational Web App, the Street Reclamation Informational Web App, the Street Rehabilitation Process Overview, and the Street Reclamation Process Overview for more information.