Highland View Area

GovDelivery envelope logo Opens in new windowSubscribe to email updates

Overview

Reconstruction (northern half) consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs. Reclamation (southern half) consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Notify Us

Click on Notify Us above to tell us about anything on your property or street related to the current projects.

Contacts

Links

Updates

Click on your street segment on the map below or see below for updates.

September 13, 2019

  • Phase 2 (Horizon Lane, Circle, and Road): Paving the first layer of asphalt has been postponed to September 18, 2019 due to weather. Paving asphalt driveways and boulevard restoration is scheduled to take place shortly after paving and is expected to take about 10 days.
  • Phase 3 (Reclamation Areas): Boulevard grading and seeding is expected to take place within the next couple weeks, weather permitting.
  • Phase 4 (Highland View Avenue, Lane, and Circle): Water main replacement is scheduled to start September 17, 2019. Homes are scheduled to be switched back to the new water main starting late in the week of September 23, 2019.

September 3, 2019

  • Phase 2 (Horizon Lane, Circle, and Road): The contractor is completing concrete driveway installations.  Grading is to occur this week. Paving is scheduled the week of September 9, 2019.
  • Phase 3 (Reclamation Areas): Final paving is tentatively scheduled early to middle October 2019.
  • Phase 4 (Highland View Avenue, Lane, and Circle): Water main installation is scheduled to start the week of September 9, 2019.  Paving and sod placement are expected to occur mid-October 2019.